The construction project progresses apace. The final pile was driven last week and the piling rig and crawler crane were stripped down and removed from…
The project is going well; the contractor worked a couple of Saturdays to make up for lost time due to strong winds. The piling is…
STV broadcast a news item about Shore Street on Friday – view it here – https://youtu.be/dsnDzcH17Sg
Delighted to report the project is now well underway. The diggers are working on the beach and the large crawler crane is now on site…
A Notice to Mariners has been published. Please see 2127 Ullapool Harbour Trustees – Notice to Mariners 2022 no.1
The pre-start meeting has taken place. All the contract paperwork has been signed and the schedule of works has been agreed. The main contractor RJ…
19 August 2022 I’m delighted to report that the paperwork debate which has dragged on for many months was finally completed on Monday 15th August.…
Pleased to report some positive progress with Transport Scotland on the contractual arrangements and VAT implications of the project. The concrete breakwater pontoons are progressing…
The project continues to gather momentum with funding secured, planning agreed and a contractor all but appointed. The works will have a slow start from…