20 December 2022

Shore Street Project Update

The works have progressed well in the past few weeks.  Piling is now complete, long reach digger dredging and rock armour revetment placement continue daily, the sea wall is taking shape and the pile cap shuttering is well developed. The contractor will finish work on Friday 23rd for two weeks, returning to site 9th January 2023. I would like to take this opportunity to thank the contractor RJ McLeod and their workforce for their hard work in delivering a tricky project efficiently with minimal impact to village life.  Visit www.ullapool-harbour.co.uk for regular updates about the project; we’ve recently uploaded a condensed timelapse video which shows progress from the very start until late last week (https://www.ullapool-harbour.co.uk/harbour-developments/).