Work continues apace. The main elements of the work which have been ongoing over the past month include rainwater drainage, road crossings, concrete seawall shuttering and pier cap formation.
The stonemasons have started work cladding the new sea wall using local stone sourced from the Corrieshalloch Gorge visitor centre project. With 174m to complete they have a big job in front of them.