27 February 2023

Work continues apace.  The main elements of the work which have been ongoing over the past month include rainwater drainage, road crossings, concrete seawall shuttering and pier cap formation.    The stonemasons have started work cladding the new sea wall using local stone sourced from the Corrieshalloch Gorge visitor centre project.  With 174m to complete […]

Read More

27 January 2023

Following the two-week Christmas holiday closure the contractor has returned to continue the promenade works and make a start on the Shore Street drainage system. Frost and snow curtailed progress for a couple of days as the quarry was unable to supply concrete or rock armour. Thankfully warmer weather is on the way and with […]