19 June 2023

The project area has progressed well and the main areas of pavement, roadway, cycleway and quayside have been re-surfaced with base coat tar. The top coat will be applied in a week’s time.  Work will be carried out overnight in order to reduce congestion and avoid the heat of the day. Paving, crossing points and the Scottish Water treatment infrastructure are all being progressed along with BT ducts and the Top Up Tap installation. The first batch of pontoons have been installed; the remainder will be on hold until the concrete breakwater arrives in approximately 10 days’ time. The Wee Pier hard standing has doubled in size in line and there are aspirations to support and grow the leisure sector locally. The end line is finally in sight.