31 March 2023

Shore Street Project Update Work continues on all fronts; the beach steps were installed last week and the two beach ramps are progressing well, the stonemasons have completed 50% of the seawall facing, kerbs are being laid on the south footway and dredging is finally underway. Foyle Dredging started work on the 20th March and […]

Read More

27 February 2023

Work continues apace.  The main elements of the work which have been ongoing over the past month include rainwater drainage, road crossings, concrete seawall shuttering and pier cap formation.    The stonemasons have started work cladding the new sea wall using local stone sourced from the Corrieshalloch Gorge visitor centre project.  With 174m to complete […]